A quality product can't be obtained without quality employees.
A quality product can't be obtained without quality employees.
Projects
KRCI has been in business for over 17 years and we've honed our craft into specialized large scale projects. From remote drainage solutions, to massive landslide repairs, all the way to multi-million dollar projects, we've been around the block a time or two. Check out a few of our favorites.
Project Name
-
Owner: Federal Highway Administration (USDOT)
-
Engineer: Federal Highway Administration (USDOT)
-
Construction of new bulb tee girder bridge including clearing, earthwork, drilled shaft foundation, CIP abutments, riprap, riparian planting, aggregate, asphalt paving, soil stabilization and temporary birdge design.
-
$6.9M
Dickey Creek Bridge Replacement
Project Name
-
Owner: City of Wenatchee
-
Engineer: City of Wenatchee
-
Renovation of existing public park, including asphalt trail paving, landscape improvements, irrigation adjustments, utility extensions, restroom facility, playground equipment installation, fencing, stage construction, splash pad installation, picnic shelter installation and other associated appurtenances and site improvements.
-
$2.6M
Lincoln Park Renovations
Project Name
-
Owner: Douglas County PUD
-
Engineer: Douglas County PUD
-
Utility installation and site work for a hydrogen processing facility
-
$4.2M + $1.1M
Hydrogen Switchyard Utility Installation & Site Grading
Project Name
-
Owner: East Wenatchee Water District
-
Engineer: RH2 Engineering
-
Build new CMU booster pump station from ground up including installing stem walls, foundation, slab, CMU walls, roofing with skylights, electrical, automatic controls, and HVAC. Retrofit altitude vault and install suction pipe header, pumps, and mechanical piping. Install piping and tie in to existing.
-
$1.2M
10th Street Booster Pump Station
Project Name
-
Owner: Chelan County
-
Engineer: Chelan County
-
Excavate and install new cast in place concrete bridge over slide area. Included structure removal, excavation, drain piping, girder installation, railing, strike bar, paving, guardrail, and structural earth wall. Included water work below the OHWM as well as channel shaping, excavation and reinforcement within slide path.
-
$2.4M
Slide Ridge Culvert Replacement
Project Name
-
Owner: Sutton Apartments LLC
-
Engineer: Torrence Engineering
-
Apartment complex and subdivision including site development, roadways and utilities
-
$3.4M
Sutton Apartments and Development Ph. 1 and Ph. 2
Project Name
-
Owner/Engineer: Federal Highway Administration
-
Repaired forest service roads significantly damaged by water runoff throughout the Okanogan-Wenatchee national forest over 10 different locations. Installed drivable dips, mechanically placed walls, riprap, and gabion walls. Replaced and cleaned existing culverts and broke down existing boulders. Re-graded and re-rocked roads after completing structure install. Established turf using mulch and dry seeding method. Satisfied rigorous federal oversight, quality control, and quality assurance metrics.
-
$850k
Okanogan-Wenatchee 2018 Repairs Phase 1
Project Name
-
Owner: WA Department of Fish & Wildlife
-
Engineer: WA Department of Fish & Wildlife
-
Install a new boat launch and parking lot. Included boring two 12” steel piles, fabricating and installing 3 steel docks, installing cast in place abutment, underwater grading and precast panel installation, installing a CXT building, regrading and paving the parking lot and entryway, and landscaping. Satisfied rigorous department of ecology oversight reporting.
-
$600k
Williams Lake Access Redevelopment
Project Name
-
Owner: Grant County
-
Engineer: Parametrix
-
Development of the 18-acre expansion landfill area around the existing landfill requiring excavation, grading, compacting, landfill composite lining system, leachate collection system installation, transfer piping systems, road construction, stormwater ditch construction and landfill gas system piping
-
$2.1M
Ephrata Landfill Phase 3 Development Project
Project Name
-
Owner: City of East Wenatchee
-
Engineer: RH2 Engineering, Inc.
-
Roundabout construction, illumination, landscaping and concrete ramp upgrades
-
$730K
3rd Street SE and Highline Drive Roundabout Improvement
Project Name
-
Owner: City of Wenatchee
-
Engineer: City of Wenatchee
-
Construct park including utilities, walls, stairs, ramps, seating, lighting, fencing, basketball court, soccer field, kiosk, shade structure, restroom and lawn finishes.
-
$2.7M
Kiwanis Park
Project Name
-
Owner: Chelan County PUD
-
Engineer: Chelan County PUD
-
Dredge Columbia River, install precast boat launch
-
$700K
Wenatchee Riverfront Boat Launch Improvements
Project Name
-
Owner: Grant County PUD
-
Engineer: Grant County PUD
-
Infrastructure improvements including boat launch, jetty, infrastructure and parking lot construction.
-
$2.2 M
Crescent Bar On-Island Improvements
Project Name
-
Owner: WSDOT
-
Engineer: WSDOT
-
Emergency Repairs of SR20 Loup Loup Pass Highway; roadway and slop rebuilding, culvert replacement
-
$1.3M + $2.5M